Oil rectifier transformer

electrical parts / electrical parts

Manufacturer:

Model:

Type of machine: Oil rectifier transformer

item-No.: 168219558

Quantity: 1

Date: 10.11.2025

Year of manufacture: 1973

Location: Land-de Germany 90552 Röthenbach

Price: 100,000 EUR

Further information is welcome by direct message, as uploading PDFs is not possible.

Info History:
The transformer is in the factory hall for changing switches.
Under the order number 490220, this was the place where a repair was carried out in 2000. Existing gas-in-oil analyses from the years 2006 – 2008 do not show any indications of disturbances in the operating behavior
Measurements and excavated action parts
Results: see Annex B
At the converter transformer 1 (StTr 1) according to Figure 1 in Appendix A, the press bar and core have already stopped at 500V, at 9V test voltage the insulation resistance is only 68kOhm. In addition, several closures of clamping screws/press iron were measured on both StTr's.

Diagnosis of the active parts
The removed active parts of the converter transformers including chokes (Figs. 11-14) and the control transformer (Figs. 2 – 3) were inspected with customer representatives on 18.03.2009.

The damage to the step selector contacts (Figs. 4 – 6 ), especially to the slip rings, was striking. According to customer information, the switches were stepped about 5.5 million times, contrary to the number of a good 335000 that can be read from the motor drive!
Figure 7 shows the load switch sets heavily contaminated with soot.
The control cabinet (Fig. 16) does not meet the current occupational safety requirements (clamping stone not covered).

Oil Analysis, DGA, D-Polymiersation Degree Determination of Paper Insulation

The results of six D polymerization degree determinations (Appendix C) indicate severe paper aging with values 267 to 429. The windings and dissipators are thermally worn! The DGA on entry into the plant confirms the results achieved in previous years with low corrosive gas concentrations.
According to the result of the insulating oil test (also in Appendix C), the oil can be reused. It is recommended to become a passivator because of the potential presence of corrosive sulfur.

Recommendations for repair
In addition to the commissioned works – including replacement of the complete tap changers,
thorough cleaning of the active parts, the boiler – the following is recommended:

- Renewal of all windings, departments.

- Attempt to remove the connections on the active parts (whereby the closure on the StTr1 press beam / core without G51264438 rewinding hardly seems to make sense because of too much effort and because of the condition of the transformer / paper aging, if its cause is not only surface dirt).

- After cleaning, the feed-through plates, which are conspicuous by signs of hot spots, can continue to be used

- Retrofitting of the control cabinet in accordance with the applicable safety regulations; Renewal of the protection and control devices, their wiring.

- Renewal of corrosion protection

After installation, the transformer must be subjected to an output test in accordance with DIN VDE 0532. It is proposed that the voltage tests be carried out at 70% of the original values, not at 75% as required by the standard in force in 1980, the year of manufacture of the transformer. This is because of the described poor condition of the windings (if a winding is not replaced). The 70% level is drawn from an older version of DIN VDE 0532, after which repeat tests had to be carried out on transformers built up to about 1973.

Share this machine on Facebook:

Inquiry

Machinery dealer?

Please remit optionally

Send wanted inquiry?

Copy to you?

Save input data

Further information is welcome by direct message, as uploading PDFs is not possible.

Info History:
The transformer is in the factory hall for changing switches.
Under the order number 490220, this was the place where a repair was carried out in 2000. Existing gas-in-oil analyses from the years 2006 – 2008 do not show any indications of disturbances in the operating behavior
Measurements and excavated action parts
Results: see Annex B
At the converter transformer 1 (StTr 1) according to Figure 1 in Appendix A, the press bar and core have already stopped at 500V, at 9V test voltage the insulation resistance is only 68kOhm. In addition, several closures of clamping screws/press iron were measured on both StTr's.

Diagnosis of the active parts
The removed active parts of the converter transformers including chokes (Figs. 11-14) and the control transformer (Figs. 2 – 3) were inspected with customer representatives on 18.03.2009.

The damage to the step selector contacts (Figs. 4 – 6 ), especially to the slip rings, was striking. According to customer information, the switches were stepped about 5.5 million times, contrary to the number of a good 335000 that can be read from the motor drive!
Figure 7 shows the load switch sets heavily contaminated with soot.
The control cabinet (Fig. 16) does not meet the current occupational safety requirements (clamping stone not covered).

Oil Analysis, DGA, D-Polymiersation Degree Determination of Paper Insulation

The results of six D polymerization degree determinations (Appendix C) indicate severe paper aging with values 267 to 429. The windings and dissipators are thermally worn! The DGA on entry into the plant confirms the results achieved in previous years with low corrosive gas concentrations.
According to the result of the insulating oil test (also in Appendix C), the oil can be reused. It is recommended to become a passivator because of the potential presence of corrosive sulfur.

Recommendations for repair
In addition to the commissioned works – including replacement of the complete tap changers,
thorough cleaning of the active parts, the boiler – the following is recommended:

- Renewal of all windings, departments.

- Attempt to remove the connections on the active parts (whereby the closure on the StTr1 press beam / core without G51264438 rewinding hardly seems to G51264438 make sense because of too much effort and because of the condition of the transformer / paper aging, if its cause is not only surface dirt).

- After cleaning, the feed-through plates, which are conspicuous by signs of hot spots, can continue to be used

- Retrofitting of the control cabinet in accordance with the applicable safety regulations; Renewal of the protection and control devices, their wiring.

- Renewal of corrosion protection

After installation, the transformer must be subjected to an output test in accordance with DIN VDE 0532. It is proposed that the voltage tests be carried out at 70% of the original values, not at 75% as required by the standard in force in 1980, the year of manufacture of the transformer. This is because of the described poor condition of the windings (if a winding is not replaced). The 70% level is drawn from an older version of DIN VDE 0532, after which repeat tests had to be carried out on transformers built up to about 1973.


seller offer No. resale 168219558
Share this machine on Facebook:

Seller

Graphite Cova GmbH

Mr Helmut Renner
90552 Röthenbach
Germany

RESALE member since 2025

Inquiry

Machinery dealer?

Please remit optionally

Send wanted inquiry?

(to all dealers for such a machine)

Copy to you?

(copy of your inquiry will be sent to your email address)

Save input data

(Save input data for further inquiries)