CHP Power Plant 800 kWe with 2xMWM TCG 2016V08 Gas Gensets
Good condition and low operating hour 800 kWe / 400 V / 50 Hz combined
heat and power (CHP) plant running on natural gas or biogas. The plant
was delivered by MWM in 2011 and it operation was closed in 2021.
Thermal energy is in form of hot water at 90°C and currently used for
district heating purpose. Due to the low amount of biogas,
cogeneration plant worked at low capacity (30-40%), and not around the
clock. It has a complete gas treatment and mixing system to utilize
biogas from landfilling which has 40 – 55 % of CH4. Power generators
are installed in two soundproof containers, TEAM Evo WMW power plant
control system and all electric switches and control cabinets are
installed in separate control room. Heat recovery system is built next
to genset containers. Both units have separate cooling radiators for
engine cooling in case of no heat load.
Main characteristics of this power plant
Made by German MWM
Commissioned in 2011
Gensets Biogas 2xMWM TCG 2016V08
Electric power production 2 x 400 kWe / 400 V / 50 Hz
Electrical efficiency 42.8% at generator poles
Therman power production 2 x 395 kWth at 90°C
NOx emission rating Max 500 mg/Nm3
Noise level 65 db (A) at 10 meters
GEN-1 OP hours and Service 19442h, E50 service made in 2015
GEN-2 OP hours and Service 11638h, E50 service made in 2016
Control system TEAM Evo WMW
Control PLC MWM DSL
Main Equipment:
• Gas Engines 2 x MWM TCG 2016 V08 C, V8 Configuration, 1500 rpm,
output 2x400 kWm
• Generators 2 x Merelli MJB 355 MB4, 400 V / 50 hz, Cos fee 1.0,
output 2 x400 kWe
• Gas train, gas mixer, voltage stabiliser, power factor controller,
control unit and switchboard
• Exhaust silencer, exhaust gas heat exanger, engine cooling systems
with plate heat exhangers for pumps and radiator air-water coolers
• Control cabinets, MMC cabinets, power switches