used
Combined Cycle Gas Turbine Power Plant 75 MW/50 Hz – Zero Hours This equipment was delivered in 2017 by an EPC contractor who selected Rolls-Royce and Siemens as main equipment suppliers. This was a greenfield project and therefore delivery contained all equipment needed for 75 MW power plant operation, like fuel gas treatment plant, water treatment plant and complete switchyard with step-up transformers Manufacturing year: 2017 Gas turbine: Rolls-Royce Trent 60, Dry Low Nox Steam turbine: Siemens SST-300 Step up tranfomers: 2 pc Alstrom 11kV to 154 kW Complete switchyard: Siemens 154 kV Nominal output 100%: 60 MW + 15 MW Max efficiency: Single cycle 42 %, combi cycle 54% Heat recovery steam boiler: 30 bar / 300 C Water treatment: Sand and active coal filters + RO Documentation: Complete original in English Delivery: Complete plant equipment from water and gas t ...